Project details

Committees

BEEM-UP

Building energy efficiency for massive market uptake

www.beem-up.eu

Start date: 01.01.2010

Duration: 48 months

Coordinator: Juan R. De las Cuevas

Budget: 7.7 M€

Details

In BEEM-UP, a total of 21 Partners from a variety of sectors collaborated over 4 years to demonstrate successful approaches for deep retrofitting with the potential for largescale replication. The project identified and implemented cost-effective 'solution packages' and delivered approximately 75% heating demand reduction in over 340 dwellings located in Sweden, France and the Netherlands.

List of achievements

Lessons learnt

Contact

Contact person: Juan Ramón de las Cuevas
Address: Acciona
Tel:
email:

Status

Finished